Showing posts with label floating wind turbine. Show all posts
Showing posts with label floating wind turbine. Show all posts

Wednesday, June 10, 2009

Floating wind turbine - -near to installation

Some while ago, I remember being rather dismissive of a floating wind turbine concept being proposed for the Minch. StatoilHydro has been approaching the problem with a rather more elegant approach, and is now close to installing the prototype 2.3 MW Hywind turbine offshore Norway. Details here.

The turbine is going into a water depth of 220 m, so the water depth is roughly twice the hub height. This may well be a solution to Norway's offshore wind needs, as the country isn't blessed with much shallow water shelf, but I'm struggling to think of suitable locations on the UKCS.

We haven't been able to find any cost information for the project though - it would be interesting to see how it stacks up against "conventional" offshore wind.

Whatever happens, we'll keep an interested eye on how the 2 year testing programme evolves.

Friday, June 13, 2008

Minch madness(?)


Just saw this in the Hebrides News. Seems like ideas for floating wind turbines are taking shape, although we remain extremely sceptical.

This new idea is for semisubmersible offshore wind turbines, generating hydrogen which they pipe to shore.

In addition to our earlier questions around the engineering challenges of floating turbines and bearing wear associated with the movement, our additional worries are:
  1. How much will the offshore to onshore hydrogen pipelines cost?

  2. Doesn't hydrolysis of seawater produce Chlorine gas - both poisonous and corrosive? How will the technology deal with this?

Monday, May 26, 2008

Floating wind technology - crazy or just mad?


StatoilHydro has just announced that it plans to spend MMNOK 400 on a floating 2.3 MW wind turbine prototype to demonstrate the potential to build windfarms in water which would otherwise be too deep.

Now, there's a couple of things here. Redfield's experience in wind turbine tower construction tells us that the turbine nacelle is extremely sensitive to its orientation. The tolerance within which turbine towers must be delivered is extremely tight, because we understand that the turbine bearings would wear irregularly causing early and expensive failure if the turbine nacelle was not absolutely horizontal in space. So we're worried that it will be very hard to orientate the nacelle with the accuracy and stability required.

Even if you can achieve this stability, that assumes that the tower doesn't move at all. We're not sure that's realistic in a 65m tower (with a 100m spar anchor). Can bearings be developed which can tolerate the accelerations at the top of a tower like this? I'm going to try to do some sums on this, as I suspect the g forces may well be much more than bearings can take.

More apocryphally, at last week's All-Energy exhibition, I noticed that StatoilHydro couldn't even get their lovely shiny model of an offshore wind farm to work properly (half of the lights and turbines weren't working). Now, if you can't even get the model to work...